Agratas shares summer progress update from Bridgwater

Published on
07 July 2026
Agratas shares summer progress update from Bridgwater
Construction activity continues to advance at the site of our UK battery manufacturing facility in Bridgwater, Somerset, with significant progress being made on key structures within the first phase of development.
Cladding installation is progressing at pace on Building One, forming the external shell of the structure and marking an important stage in its construction. As the building's outer protective layer, cladding helps shield the structure from the elements while improving insulation, weather resistance and overall building performance.
Works are also underway on the central utilities building, with cladding now being installed following the completion of the steel framework. Once operational, the building will house critical infrastructure – such as data and power supply – supporting the wider facility.
In parallel, specialist drainage systems are being installed to support the site's long-term water management strategy, ensuring the effective collection and re-routing of roof water through the development's drainage network.
As part of our commitment to responsible resource management, we’re also reusing materials generated during construction. Rock excavated during groundworks is being crushed and stockpiled for use elsewhere across the site, reducing waste and limiting the need for imported materials.
Watch as Ryan English, our Project Manager – Capital Projects, takes us through the latest site update and highlights the progress being made at our Bridgwater facility.